Attenuation system – 900mm diameter pipework together with 2.5m diameter sumped chambers up to 3m deep including flow control gates were installed throughout the site to suit with the large volume of surface water from the new 3G pitch, car parking areas and rain water systems.
Drainage – installation of a complete foul water treatment plant along with the installation of a large interceptor tank to accommodate with any pollution from the car parking areas. These systems fed through into the attenuation system.
Section 184 – To accommodate the increased volume of anticipated traffic to the new club, a new access road was installed onto the existing highway. This was challenging due to the topographical nature of the site and the highway as it was elevated from site. Traffic management systems were used along with footpath diversions to enable the works.
Car park- to be reduced to achieve the correct ground levels. This was predominantly hard rock and so over sized excavators with ripper attachments and hydraulic breakers were used.
Foundations – the natural strata changed where the foundations of the club house was cited therefore deep excavations were required over 3m deep
Our client was impressed by how we managed the surface water whilst carrying out the deep excavations for the attenuation systems. Careful management of access on and off the site for materials and other contractors whilst installing the new road in and onto the highways
“Stringfellows ensured that work did not grind to a holt on site during the winter months by continuously maintaining access through the site for deliveries /trades despite boggy conditions. This proved to be invaluable for us to achieve deadlines and a priority we had not foreseen. Something we would give as a word of advice to others considering similar projects. Its important you have a team like Stringfellows who are willing to support in unforeseen / unexpected situations”