Bulk Excavation

Bulk excavation is the large-scale removal of soil, rock, or other materials from a construction site to create space for further construction. 

Bulk excavation is a vital step in construction, involving the removal of large amounts of material from the site. It’s usually done on a larger scale than individual foundation digging or utility trenching, preparing the site for building foundations, underground structures, or other developments.

Why choose us for your bulk excavation?

Our bulk excavation service is designed to sculpt the ideal surface and contour for your project, no matter the size.

We know just how important it is for your construction project to start on a prepared surface, so our service is geared towards creating the optimal foundation. We use the latest innovations in excavator equipment, and can quote for any size project.

 

How we can help you

Our experienced and professional team can complete a range of bulk excavation services on your behalf, including:

 

 

Landfill

Our skilled team ensures meticulous planning and execution to maximise landfill capacity while adhering to environmental regulations. With a commitment to responsible waste management, we employ innovative techniques to compact and layer materials, optimising space utilisation within the landfill.

Landfill

Parking Areas

We specialise in the development of parking areas, seamlessly conducting site strip operations on greenfield sites with a focus on minimising dig excavation for a sustainable approach.

Parking Area Excavation

Case Study

Services: Bulk Excavation & Site clearance

Client: Cascade UK Ltd

Location: Openshaw, Manchester

Project value: £75k

Contract period: 4 weeks

Project Overview:

Global business, Cascade offer versatile attachments, forks, masts and related technologies. Their large scale industrial manufacturing facility with yard had a stock pile of historic excavation derived from extending their facilities in various stages over previous years

Background:

Now needing to extend once again, meant they needed to eliminate the stock pile from site which included segregating steel, vegetation, hardcore and soil
Client had concerns about their continued business of daily steel deliveries and manufactured goods being transported off site whilst the work was being undertaken.

Scope of work;

25 ton excavator was used to carry out the bulk excavation along with our fleet of muck shift wagons allowing us to remove around 600 ton per day, totalling 12000 tons over the 4 week project. All scrap steel was segregated and recycled and green waste was disposed of independently